Typical Projects
|
|
- 12” Concrete Coated Pipeline Lowering in Beach, Shoal, and Bay Areas through reefs, sand, and soil, including hydro testing and re-commissioning
- Mainline Valve Replacement, 3’ Water Depth (Beach/Bay Area)
- Pipeline Cleaning and Re-commissioning, 8 miles-4’ (Marsh/Swamp area)
- 2-Complete Well, Line heater, Flowline, and Pipeline installation (Marsh/Bay Area)
- Removal of abandoned Transmission Laterals and Flow lines for regulated pipeline companies, in Environmentally Sensitive Marsh Area
- Mainline Valve Station Site Restoration and Shoreline Mat installation, 3’-0’ Water Depth
- 12” Concrete Coated Pipeline Lowering in Bay Areas (across the head of passes)
- Upgrade and Hydrotest of 5-8”, 12”, and 16” - LPG Pipelines (16 miles), (Land and Inland Marine)
- Installation of 1,300’ of Vinyl bulkhead for shoreline protection in Environmentally Sensitive Marsh Area
- Transmission Company Interconnect to Other Transmission Company with platform, piping, and SCADA retrofit in Environmentally Sensitive Marsh Area
- Transmission Company Meter Stations for lateral tie-ins
- 30” HCA Project – Replacement of 3,000’ (Land)
- 20” Diameter Atchafalaya River Directional Drill Pipeline Replacement (Swamp to Swamp)
- Shoreline Restoration at Pipeline Approaches including rocks and bulkheads
- Pipeline System Sign, Bulkhead, and Rock Installation (Marsh Areas Across Louisiana)
- 14” Pipeline Removal across Lake Pontchartrain (90,000’)
- 12” Transmission Pipeline across Marsh Fields 55,000’ Concrete Coating
- 12” Anomaly Repairs (Land, Water and Marsh)
- Mainline Compressor Station Installations
|
|
|
|